In which phase of the DSDM process is quality not normally considered?

  1. Feasibility

  2. Deployment

  3. Pre-Project

  4. Foundations

The correct answer is: Pre-Project

In the DSDM (Dynamic Systems Development Method) process, the Pre-Project phase is primarily focused on determining whether a project is viable and worth pursuing. The main concerns during this phase include assessing business needs, defining project objectives, and ensuring alignment with organizational goals. Quality considerations are typically not a primary focus at this stage because the team is still exploring the potential of the project rather than defining how to deliver a quality product. Quality becomes a more pertinent concern in later phases, such as Foundations, where establishing requirements and defining deliverables take place, and throughout the development phases leading to Deployment, where actual product delivery is managed. In these later stages, rigorous quality assurance and testing practices are vital to ensure the final product meets the necessary standards and customer expectations. Thus, in Pre-Project, the emphasis is not on quality but rather on project viability, making it the phase where quality is not normally considered.